Highway 70 between Grande-Anse and the Bay

As part of the extension of Highway 70, between Chemin de la Grande-Anse and La Baie, Forage CBF was mandated for the construction of the north and south overpasses.

Client

Construction J & R Savard Ltd

Expertise(s)

Caisson Piles
Bored piles
Anchoring Systems
Rock Anchors

Location

Saguenay

Year

2022

Raise your expertise to the level of expert consultant

48" caissons

16

Total length of 16 in. diameter bored piles

5700

Total length of 20 in diameter bored piles

3300

Combine strategic vision and technical mastery on each project

These infrastructures will allow the extension of the highway over the Roberval-Saguenay Railway Company's railway line, thus ensuring better transport fluidity and sustainable infrastructure.

A job done according to the rules of the art

To ensure the stability of these structures, we installed 16 48-inch diameter caisson piles, with a drilling depth varying between 10 m and 45 m and a 2.5-inch rock socket. In addition, 96 20-inch bored piles were installed, with lengths ranging from 10 m to 40 m. In addition, 228 16-inch bored piles were embedded in the rock, with depths varying between 10 m and 40 m. To further enhance stability, 8 rock anchors were installed inside the 48-inch caisson piles, incorporating two 65 mm anchor bars per borehole, with a borehole of 8 m below the bottom of the caisson piles.

Thanks to our expertise in deep foundations and anchors, we were able to meet the technical challenges imposed by this large-scale project, thus guaranteeing solid and sustainable infrastructure.