Deep Foundations
As part of the Station 148 Compressor Unit Addition à The CedarsForage CBF was commissioned to carry out deep foundations and retaining structures in order to guarantee the stability of TC Energy.
Client
Ganotec
Expertise(s)
Driven piles
Sheet piles
Sheet pile support
Location
The Cedars
Year
2020
Raise your expertise to the level of expert consultant
Number of piles driven
Total length of piles installed
Sheet pile support
Combine strategic vision and technical mastery on each project
The work included the installation of several friction driven piles, with varying diameters: 8.625 in, 10.75 in, 12.75 in and 16 in.
A job done according to the rules of the art
The piles required extensions to reach the required depths, reaching 44 meters deep. In addition, sheet pile support was installed over 460 linear meters, with a shoring system to ensure optimal strength.
Thanks to our expertise in driven piles and support, we contributed to the creation of sustainable and secure infrastructure adapted to the requirements of this energy project.